Calgary Green Line downtown alignment milestones

Sources checked

Trace the route from the tunnel to 10 Avenue SThree downtown alignments considered for the Green Line
  1. 2021
    Original Phase 1 funding approved

    Downtown deep tunnel from 4 Street SE to Eau Claire Source 1

  2. 2024
    Council shortens the first phase

    Tunnel retained in the shortened proposal Source 1

  3. December 2024
    Alberta publishes Baseline Elevated Concept

    10 Avenue S then north on 2 Street SW to 7 Avenue S Source 1

  4. January 2025
    Council orders functional planning

    Based on the elevated concept Source 1

  5. June 2025
    Southeast construction starts

    Shepard to Event Centre/Grand Central Station Source 2

  6. 8 September 2026
    Executive Committee favours surface route

    10 Avenue S to 2 Street SW Source 1

Show 1 more dates
  1. 22 September 2026
    City Council approves downtown alignment

    Surface segment goes into design, planning and procurement Source 1

The City’s southeast construction package and its downtown route design appear as separate milestones.

Source 1 Source 2 Source 3

Calgary Green Line downtown alignment milestones

The route and funding records describe Phase 1 as Calgary currently presents it. Historical designs show earlier scopes. The downtown route decision authorises the current alignment, while detailed engineering and procurement are continuing.

7 records
Source
2021Original Phase 1 funding approvedDowntown deep tunnel from 4 Street SE to Eau ClaireSource 1
2024Council shortens the first phaseTunnel retained in the shortened proposalSource 1
December 2024Alberta publishes Baseline Elevated Concept10 Avenue S then north on 2 Street SW to 7 Avenue SSource 1
January 2025Council orders functional planningBased on the elevated conceptSource 1
June 2025Southeast construction startsShepard to Event Centre/Grand Central StationSource 2
8 September 2026Executive Committee favours surface route10 Avenue S to 2 Street SWSource 1
22 September 2026City Council approves downtown alignmentSurface segment goes into design, planning and procurementSource 1