Champlain Hudson Power Express delivery and construction milestones

Sources checked

Track the Champlain Hudson milestonesFrom New York supply agreement to electricity delivery
  1. November 2021
    Hydro-Québec reaches New York supply agreement

    Contract with the New York State Energy Research and Development Authority Source 2

  2. 30 November 2022
    CHPE construction starts

    US transmission works begin Source 1

  3. August 2025
    Last Lake Champlain cable section installed

    Cable crews finish laying the stretch into Putnam Station Source 1

  4. January 2026
    Major CHPE construction complete

    Restoration continues along the route Source 1

  5. 13 May 2026
    CHPE becomes operational

    Developer’s technical operating milestone Source 1

  6. 1 June 2026
    Hydro-Québec starts contracted deliveries

    Power delivery begins under the 2021 agreement Source 2

Show 1 more dates
  1. 16 June 2026
    Developer marks project completion

    1,250 MW link to New York City Source 3

Construction, technical operation and deliveries under the power contract have separate dates.

Source 1 Source 2 Source 3

Champlain Hudson Power Express delivery and construction milestones

The developer’s 339 miles cover the US cable from the border to Astoria. Hydro-Québec’s more than 600 kilometres include the Canadian connection from its Hertel substation. A megawatt rating measures power capacity, rather than energy delivered.

7 records
Source
November 2021Hydro-Québec reaches New York supply agreementContract with the New York State Energy Research and Development AuthoritySource 2
30 November 2022CHPE construction startsUS transmission works beginSource 1
August 2025Last Lake Champlain cable section installedCable crews finish laying the stretch into Putnam StationSource 1
January 2026Major CHPE construction completeRestoration continues along the routeSource 1
13 May 2026CHPE becomes operationalDeveloper’s technical operating milestoneSource 1
1 June 2026Hydro-Québec starts contracted deliveriesPower delivery begins under the 2021 agreementSource 2
16 June 2026Developer marks project completion1,250 MW link to New York CitySource 3