Contrecœur container terminal permissions, financing and works milestones

Sources checked

Québec port expansionContrecœur container terminal permissions, financing and works milestones
  1. 11 September 2025
    Major Projects Office referral

    Ottawa referred the project for federal coordination. Source 1

  2. 9 October 2025
    Preparatory works begin

    The port also awarded the in-water works contract. Source 1

  3. 16 October 2025
    Fish habitat offset authorisation

    Fisheries and Oceans Canada authorised work to create additional copper redhorse feeding grounds. Source 1

  4. 5 January 2026
    Second fisheries authorisation

    The approval addressed the effects of in-water works and wharf construction on fish and habitat. Source 1

  5. 26 February 2026
    Project borrowing order

    An order in council approved provisions for a CAD 1.16 billion borrowing limit, plus interest. Source 2

  6. 6 April 2026
    Financing details finalised

    The port and Canada Infrastructure Bank settled the financing details before the 9 April announcement. Source 1

Show 1 more dates
  1. 14 August 2026
    In-water construction announced

    Work covered the jetty, terminal wharf and related marine infrastructure. Source 1

Preparatory work began in 2025. Construction of marine structures followed in 2026.

Source 1 Source 2

Contrecœur container terminal permissions, financing and works milestones

The Major Projects Office dates the work phases and fisheries authorisations. The order in council records a project-specific borrowing limit.

7 records
Source
11 September 2025Major Projects Office referralOttawa referred the project for federal coordination.Source 1
9 October 2025Preparatory works beginThe port also awarded the in-water works contract.Source 1
16 October 2025Fish habitat offset authorisationFisheries and Oceans Canada authorised work to create additional copper redhorse feeding grounds.Source 1
5 January 2026Second fisheries authorisationThe approval addressed the effects of in-water works and wharf construction on fish and habitat.Source 1
26 February 2026Project borrowing orderAn order in council approved provisions for a CAD 1.16 billion borrowing limit, plus interest.Source 2
6 April 2026Financing details finalisedThe port and Canada Infrastructure Bank settled the financing details before the 9 April announcement.Source 1
14 August 2026In-water construction announcedWork covered the jetty, terminal wharf and related marine infrastructure.Source 1