Aspen progress snapshots with both reported completion measures

Sources checked

Progress percentagesConstruction compared with overall project completion

Construction (%)

Shared scale · 0% to 88%

  • 1 July 202520%
  • February 202644%
  • 31 July 202682%

Switch between construction and overall project progress. The same three reporting dates appear in both views.

Source 1 Source 2

Aspen progress snapshots with both reported completion measures

The project and construction percentages are SaskPower’s estimates. The table includes only updates that reported both measures. July 2025 is approximate.

3 records
Source
1 July 20252042Gas turbine generator arrived on 25 JuneSource 1
February 20264463Engineering at 95%, and 93% of procurements awardedSource 1
31 July 20268288SaskPower reports 2.8 million hours worked on siteSource 1