Source data
Site C hydroelectric project approvals and operating milestones
Sources checked
- October 2014Environmental approvals
Federal and provincial governments approved the project. Source 1
- July 2015Construction starts
Work began on the Peace River site near Fort St. John. Source 2
- October 2020Peace River diverted
Temporary tunnels carried river water past the construction area. Source 3
- 25 August 2024Reservoir filling begins
BC Hydro reported that the areas needed for filling were ready. Source 2
- October 2024First unit starts generating
The first of the six units came into service while reservoir filling was under way. Source 4
- 8 August 2025Sixth unit commissioned
BC Hydro lists the station as fully operational from this date. Source 1
First generation began in October 2024. All six units were operating by August 2025.
Site C hydroelectric project approvals and operating milestones
Milestones describe the Site C project near Fort St. John, British Columbia. The operating facility is now called the John Horgan Dam and Generating Station.
| Source | |||
|---|---|---|---|
| October 2014 | Environmental approvals | Federal and provincial governments approved the project. | Source 1 |
| July 2015 | Construction starts | Work began on the Peace River site near Fort St. John. | Source 2 |
| October 2020 | Peace River diverted | Temporary tunnels carried river water past the construction area. | Source 3 |
| 25 August 2024 | Reservoir filling begins | BC Hydro reported that the areas needed for filling were ready. | Source 2 |
| October 2024 | First unit starts generating | The first of the six units came into service while reservoir filling was under way. | Source 4 |
| 8 August 2025 | Sixth unit commissioned | BC Hydro lists the station as fully operational from this date. | Source 1 |
Source links
- BC Hydro operating profile for the John Horgan Dam and Generating Station
- BC Hydro reservoir filling announcement
- BC Hydro Site C annual report to the British Columbia Utilities Commission
- BC Hydro commissioning announcement
- Federal and provincial Joint Review Panel summary
- BC Hydro 2024 to 2025 service plan report