Selected milestones in Wataynikaneyap Power's Ontario transmission project

Sources checked

Follow the transmission line and community connectionsSelected milestones in Wataynikaneyap Power's Ontario transmission project
  1. 20 December 2018
    Pikangikum connected

    First community on the system to connect to the Ontario grid. Source 1

  2. 17 January 2019
    Ownership partnership expanded

    Two First Nations joined, increasing the First Nation partners from 22 to 24. Source 2

  3. 29 October 2019
    Financial close announced

    Operator issued notice to proceed to Valard for the broader project. Source 3

  4. 16 August 2022
    First phase energisation announced

    About 300 km of 230 kV line between Dinorwic and Pickle Lake. Source 4

  5. 13 December 2024
    Transmission system energisation reported

    Operator said all main system assets were energised and 12 communities had completed connections. Source 5

  6. 17 December 2024
    Poplar Hill connected

    The federal government reported the 13th community connection. Source 6

Show 1 more dates
  1. 9 April 2026
    Muskrat Dam connected

    The operator reported its 16th community connection and the last under the current engineering, procurement and construction contract. Source 7

The line, substations and individual community connections each have their own milestones.

Source 1 Source 2 Source 3 Source 4 Source 5 Source 6 Source 7

Selected milestones in Wataynikaneyap Power's Ontario transmission project

Dates identify connections, announcements or completed infrastructure as described in each record. The operator distinguishes community connections from energisation of transmission assets.

7 records
Source
20 December 2018Pikangikum connectedFirst community on the system to connect to the Ontario grid.Source 1
17 January 2019Ownership partnership expandedTwo First Nations joined, increasing the First Nation partners from 22 to 24.Source 2
29 October 2019Financial close announcedOperator issued notice to proceed to Valard for the broader project.Source 3
16 August 2022First phase energisation announcedAbout 300 km of 230 kV line between Dinorwic and Pickle Lake.Source 4
13 December 2024Transmission system energisation reportedOperator said all main system assets were energised and 12 communities had completed connections.Source 5
17 December 2024Poplar Hill connectedThe federal government reported the 13th community connection.Source 6
9 April 2026Muskrat Dam connectedThe operator reported its 16th community connection and the last under the current engineering, procurement and construction contract.Source 7