Source data
Cedar LNG construction and delivery milestones
Sources checked
- 25 June 2024Final investment decision
Partners commit to the floating LNG development Source 1
- After June 2024Onshore construction starts
Site preparation and clearing in Kitimat Source 2
- April 2025Pipeline contractor selected
Ledcor Haisla Limited Partnership selected for the pipeline scope Source 3
- June 2025Floating vessel fabrication announced
Work begins at the Samsung Heavy Industries shipyard in South Korea Source 3
- 21 October 2026Developer reports overall progress
More than 70% complete, across the combined project Source 4
- Late 2028Anticipated in-service date
Operating target for the facility near Kitimat Source 4
The October progress figure describes the overall project.
Cedar LNG construction and delivery milestones
Progress percentages and dates are company-reported. The late-2028 service date and annual nameplate capacity are project targets.
| Source | |||
|---|---|---|---|
| 25 June 2024 | Final investment decision | Partners commit to the floating LNG development | Source 1 |
| After June 2024 | Onshore construction starts | Site preparation and clearing in Kitimat | Source 2 |
| April 2025 | Pipeline contractor selected | Ledcor Haisla Limited Partnership selected for the pipeline scope | Source 3 |
| June 2025 | Floating vessel fabrication announced | Work begins at the Samsung Heavy Industries shipyard in South Korea | Source 3 |
| 21 October 2026 | Developer reports overall progress | More than 70% complete, across the combined project | Source 4 |
| Late 2028 | Anticipated in-service date | Operating target for the facility near Kitimat | Source 4 |