Cedar LNG construction and delivery milestones

Sources checked

Track work on the vessel and the shoreCedar LNG’s offshore fabrication and Kitimat construction
  1. 25 June 2024
    Final investment decision

    Partners commit to the floating LNG development Source 1

  2. After June 2024
    Onshore construction starts

    Site preparation and clearing in Kitimat Source 2

  3. April 2025
    Pipeline contractor selected

    Ledcor Haisla Limited Partnership selected for the pipeline scope Source 3

  4. June 2025
    Floating vessel fabrication announced

    Work begins at the Samsung Heavy Industries shipyard in South Korea Source 3

  5. 21 October 2026
    Developer reports overall progress

    More than 70% complete, across the combined project Source 4

  6. Late 2028
    Anticipated in-service date

    Operating target for the facility near Kitimat Source 4

The October progress figure describes the overall project.

Source 1 Source 2 Source 3 Source 4

Cedar LNG construction and delivery milestones

Progress percentages and dates are company-reported. The late-2028 service date and annual nameplate capacity are project targets.

6 records
Source
25 June 2024Final investment decisionPartners commit to the floating LNG developmentSource 1
After June 2024Onshore construction startsSite preparation and clearing in KitimatSource 2
April 2025Pipeline contractor selectedLedcor Haisla Limited Partnership selected for the pipeline scopeSource 3
June 2025Floating vessel fabrication announcedWork begins at the Samsung Heavy Industries shipyard in South KoreaSource 3
21 October 2026Developer reports overall progressMore than 70% complete, across the combined projectSource 4
Late 2028Anticipated in-service dateOperating target for the facility near KitimatSource 4