How Cedar LNG is building a floating plant and a Kitimat terminal

Cedar LNG reports that construction of its Indigenous majority-owned project was more than 70% complete in October 2026. The floating plant is being built in South Korea while pipeline and terminal work advances in British Columbia.

Sources checked

Track work on the vessel and the shoreCedar LNG’s offshore fabrication and Kitimat construction
  1. 25 June 2024
    Final investment decision

    Partners commit to the floating LNG development Source 1

  2. After June 2024
    Onshore construction starts

    Site preparation and clearing in Kitimat Source 2

  3. April 2025
    Pipeline contractor selected

    Ledcor Haisla Limited Partnership selected for the pipeline scope Source 3

  4. June 2025
    Floating vessel fabrication announced

    Work begins at the Samsung Heavy Industries shipyard in South Korea Source 3

  5. 21 October 2026
    Developer reports overall progress

    More than 70% complete, across the combined project Source 4

  6. Late 2028
    Anticipated in-service date

    Operating target for the facility near Kitimat Source 4

The October progress figure describes the overall project.

Source 1 Source 2 Source 3 Source 4

The floating facility and shore works are separate packages

The Haisla Nation and Pembina approved a floating liquefied natural gas facility in June 2024. Samsung Heavy Industries and Black & Veatch were chosen for the floating plant. Site preparation and clearing proceeded around Kitimat while the floating unit moved through shipyard fabrication in South Korea. Source 1 Source 2 Source 3

The shore package has to connect gas, electricity and shipping

Cedar LNG reports a transport agreement for 400 million cubic feet of natural gas per day through Coastal GasLink. Its transmission line is intended to bring power from the Minette Bay substation to the floating unit. A marine terminal then connects the facility to vessels in Douglas Channel. Source 1 Source 3 Source 2

The construction model has several funding measures

At the investment decision, the developer estimated total project cost at about US$4.0 billion, including about US$3.4 billion of capital costs and US$0.6 billion for construction interest and transaction costs. It expected roughly 60% of project cost to be financed by asset-level debt. These figures were disclosed as investment-decision estimates. Source 1

The October percentage covers the whole development

Cedar LNG said the project was more than 70% complete in its October update and retained late 2028 as its expected operating date. The plant’s 3.3 million tonnes per year is its planned nameplate capacity. Overall construction progress does not establish when each individual facility will be ready or how much LNG will ship. Source 4 Source 1