Darlington first small reactor assessment and licensing milestones

Sources checked

Ontario infrastructure approvalsDarlington first small reactor assessment and licensing milestones
  1. 2012
    Environmental assessment completed

    The federal decision addressed the wider proposed Darlington project. Source 1

  2. December 2021
    Reactor design selected

    Ontario Power Generation selected the BWRX-300. Source 1

  3. October 2022
    Construction application filed

    The application requested a licence for one reactor. Source 1

  4. 19 April 2024
    Assessment found applicable

    The commission determined that a new environmental assessment was unnecessary for the selected design. Source 1

  5. October 2024 and January 2025
    Public hearing held

    The commission held two parts of the construction-licence hearing. Source 1

  6. 4 April 2025
    Construction licence announced

    The licence covers one reactor and is valid to 31 March 2035. Source 1

Show 1 more dates
  1. 23 June 2026
    Loan guarantee transaction announced

    Canada and Ontario announced financing support for an eventual Williams Treaties First Nations minority interest. Source 2

The 2025 decision authorises construction of one reactor, with a licence running to March 2035.

Source 1 Source 2

Darlington first small reactor assessment and licensing milestones

The timeline follows the first reactor construction licence and a later ownership-financing announcement. The original environmental assessment covered a wider proposed project.

7 records
Source
2012Environmental assessment completedThe federal decision addressed the wider proposed Darlington project.Source 1
December 2021Reactor design selectedOntario Power Generation selected the BWRX-300.Source 1
October 2022Construction application filedThe application requested a licence for one reactor.Source 1
19 April 2024Assessment found applicableThe commission determined that a new environmental assessment was unnecessary for the selected design.Source 1
October 2024 and January 2025Public hearing heldThe commission held two parts of the construction-licence hearing.Source 1
4 April 2025Construction licence announcedThe licence covers one reactor and is valid to 31 March 2035.Source 1
23 June 2026Loan guarantee transaction announcedCanada and Ontario announced financing support for an eventual Williams Treaties First Nations minority interest.Source 2