How Darlington’s first small reactor reached a construction licence

The Canadian Nuclear Safety Commission issued a licence to construct one BWRX-300 reactor at Darlington in April 2025. Ontario Power Generation had applied in 2022 after selecting the design the previous year.

Sources checked

Ontario infrastructure approvalsDarlington first small reactor assessment and licensing milestones
  1. 2012
    Environmental assessment completed

    The federal decision addressed the wider proposed Darlington project. Source 1

  2. December 2021
    Reactor design selected

    Ontario Power Generation selected the BWRX-300. Source 1

  3. October 2022
    Construction application filed

    The application requested a licence for one reactor. Source 1

  4. 19 April 2024
    Assessment found applicable

    The commission determined that a new environmental assessment was unnecessary for the selected design. Source 1

  5. October 2024 and January 2025
    Public hearing held

    The commission held two parts of the construction-licence hearing. Source 1

  6. 4 April 2025
    Construction licence announced

    The licence covers one reactor and is valid to 31 March 2035. Source 1

Show 1 more dates
  1. 23 June 2026
    Loan guarantee transaction announced

    Canada and Ontario announced financing support for an eventual Williams Treaties First Nations minority interest. Source 2

The 2025 decision authorises construction of one reactor, with a licence running to March 2035.

Source 1 Source 2

The original assessment covered a wider proposal

The regulator describes the Darlington project as including up to four new reactors at the existing nuclear site in Clarington. The federal environmental assessment was completed in 2012. The commission revisited its applicability after the operator selected the BWRX-300 design. Source 1

The construction application covered one unit

Ontario Power Generation applied for one construction licence in October 2022. The commission considered it at public hearings in October 2024 and January 2025. The resulting licence covers the first unit and includes site-specific conditions. Source 1

Consultation formed part of the licensing decision

The commission says the licensing decision engaged the Crown’s duty to consult. It concluded that the duty had been met in relation to the decision and directed measures to incorporate Indigenous knowledge and practices into licensed activities and oversight. Source 1

Financing and licensing are separate milestones

The Major Projects Office profile records a June 2026 loan guarantee transaction supporting about CAD 715 million in financing for seven Williams Treaties First Nations to acquire an eventual minority interest. That announcement concerns project ownership and financing. The construction decision describes the scope of authorised work. Source 2 Source 1