Montréal REM public opening phases and subsequent development stages

Sources checked

Regular service expanded across three opening datesMontréal REM public opening phases and subsequent development stages
  1. 31 July 2023
    South Shore service begins

    5 · 5 Source 1

  2. 17 November 2025
    Downtown to Deux-Montagnes expansion

    14 · 19 Source 2

  3. 18 May 2026
    Anse-à-l'Orme branch opens

    4 · 23 Source 3

  4. 16 June 2026
    Planning for two infill stations announced

    0 · 23 Source 4

  5. 22 October 2026
    Operator reports new airport testing milestone

    0 · 23 Source 5

  6. 2027 target
    Airport branch scheduled

    2 planned · Future phase Source 6

The last three milestones are planning, testing and a future target. They do not add open stations.

Source 1 Source 2 Source 3 Source 4 Source 5 Source 6

Montréal REM public opening phases and subsequent development stages

Cumulative counts add only the three reported service openings. Two airport stations and two infill stations are at different future development stages.

6 records
Source
31 July 2023South Shore service begins55Source 1
17 November 2025Downtown to Deux-Montagnes expansion1419Source 2
18 May 2026Anse-à-l'Orme branch opens423Source 3
16 June 2026Planning for two infill stations announced023Source 4
22 October 2026Operator reports new airport testing milestone023Source 5
2027 targetAirport branch scheduled2 plannedFuture phaseSource 6