How Montréal's REM opened 23 stations in three phases
Montréal's Réseau express métropolitain put five stations into service in July 2023, 14 more in November 2025 and four more in May 2026. The airport branch entered testing and remains scheduled for 2027.
Sources checked
- 31 July 2023South Shore service begins
5 · 5 Source 1
- 17 November 2025Downtown to Deux-Montagnes expansion
14 · 19 Source 2
- 18 May 2026Anse-à-l'Orme branch opens
4 · 23 Source 3
- 16 June 2026Planning for two infill stations announced
0 · 23 Source 4
- 22 October 2026Operator reports new airport testing milestone
0 · 23 Source 5
- 2027 targetAirport branch scheduled
2 planned · Future phase Source 6
The last three milestones are planning, testing and a future target. They do not add open stations.
Opening weekend and regular service had separate dates
The South Shore section was inaugurated on 28 July 2023 and held public trial rides over the weekend. Regular service began on 31 July. The timeline uses the start of service for the count, which was five stations from Brossard to Gare Centrale. Source 1
The largest step was the Deux-Montagnes opening
The November 2025 phase added 14 stations and made it possible to travel on REM between the South Shore and North Shore. That one phase accounts for 14 of the 23 stations opened in the three documented service launches. Source 2 Source 1 Source 3
The West Island opening came before the airport branch
The Anse-à-l'Orme branch added four stations on 18 May 2026. The operator separately identifies Marie-Curie and the YUL airport station as part of the airport branch. Its schedule lists that branch for 2027, and its October update records testing progress. Source 3 Source 6 Source 5
Two more stations entered planning
The June 2026 announcement launched planning for Griffintown-Bernard-Landry and a second station near Bridge and Wellington streets. REM says the first was already part of the original alignment and the second still needed an exact location and name. Both remain separate from the service opening count. Source 4
Sources
- REM South Shore service inauguration and start
- REM official opening of 14 stations, 17 November 2025
- REM confirms West Island service, 18 May 2026
- REM announces planning for two additional stations
- REM airport branch testing update, 22 October 2026
- REM network commissioning schedule and airport station plans