PowerCo St. Thomas project announcements and construction stages

Sources checked

Construction milestones and successive operating targetsPowerCo St. Thomas project announcements and construction stages
  1. 13 March 2023
    St. Thomas selected

    Volkswagen's first overseas battery cell plant Source 1

  2. 28 October 2025
    Start of construction announced

    Foundations for three buildings, initial production targeted for 2027 Source 2

  3. 2026 federal briefing
    Construction status recorded

    Government briefing listed an expected 2028 start Source 3

  4. 24 September 2026
    EllisDon appointed

    PowerCo outlines next construction phase and 2029 operations target Source 4

  5. 2029 target
    Expected start of operations

    Company's latest stated target in its September update Source 4

The September 2026 contractor announcement set a new operations target while confirming continued work.

Source 1 Source 2 Source 3 Source 4

PowerCo St. Thomas project announcements and construction stages

Production and operations dates are the terms each source uses for its targets. The sources give different dates at different points in the project's development.

5 records
Source
13 March 2023St. Thomas selectedVolkswagen's first overseas battery cell plantSource 1
28 October 2025Start of construction announcedFoundations for three buildings, initial production targeted for 2027Source 2
2026 federal briefingConstruction status recordedGovernment briefing listed an expected 2028 startSource 3
24 September 2026EllisDon appointedPowerCo outlines next construction phase and 2029 operations targetSource 4
2029 targetExpected start of operationsCompany's latest stated target in its September updateSource 4