PowerCo Canada appointed EllisDon as general contractor on 24 September 2026 and moved the expected start of operations to 2029. Its construction announcement a year earlier had targeted initial production in 2027.

Sources checked

Construction milestones and successive operating targetsPowerCo St. Thomas project announcements and construction stages
  1. 13 March 2023
    St. Thomas selected

    Volkswagen's first overseas battery cell plant Source 1

  2. 28 October 2025
    Start of construction announced

    Foundations for three buildings, initial production targeted for 2027 Source 2

  3. 2026 federal briefing
    Construction status recorded

    Government briefing listed an expected 2028 start Source 3

  4. 24 September 2026
    EllisDon appointed

    PowerCo outlines next construction phase and 2029 operations target Source 4

  5. 2029 target
    Expected start of operations

    Company's latest stated target in its September update Source 4

The September 2026 contractor announcement set a new operations target while confirming continued work.

Source 1 Source 2 Source 3 Source 4

Three records carry three different targets

PowerCo's October 2025 release targeted initial production in 2027. A federal briefing in 2026 recorded an expected 2028 start. PowerCo's September 2026 update subsequently named 2029 as the expected start of operations. Each date belongs to a distinct source and stage of planning. Source 2 Source 3 Source 4

The contractor packages changed as the site advanced

Magil Construction led foundational work for three buildings spanning about 850,000 square feet, according to the 2025 release. The September 2026 update identifies EllisDon as general contractor for the next phase, covering the production-building shell, utility systems and other site infrastructure. Source 2 Source 4

Worker numbers refer to different stages

PowerCo reported around 60 EllisDon workers on site in September and expected around 1,300 at peak. The federal briefing's 3,000 employment figure was reported separately alongside the project announcement. The September count covers one contractor at a point in time and cannot measure eventual operating jobs. Source 3 Source 4

Why the production target matters

The developer says the revised date allows it to align battery technology and the pace of expansion with expected market demand. It continues to build core infrastructure while retaining flexibility about how the plant scales. The 2029 target records that updated development plan. Source 4