Canada · Industrial projects
PowerCo moved its St. Thomas battery plant start to 2029 as work continued
PowerCo Canada appointed EllisDon as general contractor on 24 September 2026 and moved the expected start of operations to 2029. Its construction announcement a year earlier had targeted initial production in 2027.
Sources checked
- 13 March 2023St. Thomas selected
Volkswagen's first overseas battery cell plant Source 1
- 28 October 2025Start of construction announced
Foundations for three buildings, initial production targeted for 2027 Source 2
- 2026 federal briefingConstruction status recorded
Government briefing listed an expected 2028 start Source 3
- 24 September 2026EllisDon appointed
PowerCo outlines next construction phase and 2029 operations target Source 4
- 2029 targetExpected start of operations
Company's latest stated target in its September update Source 4
The September 2026 contractor announcement set a new operations target while confirming continued work.
Three records carry three different targets
PowerCo's October 2025 release targeted initial production in 2027. A federal briefing in 2026 recorded an expected 2028 start. PowerCo's September 2026 update subsequently named 2029 as the expected start of operations. Each date belongs to a distinct source and stage of planning. Source 2 Source 3 Source 4
The contractor packages changed as the site advanced
Magil Construction led foundational work for three buildings spanning about 850,000 square feet, according to the 2025 release. The September 2026 update identifies EllisDon as general contractor for the next phase, covering the production-building shell, utility systems and other site infrastructure. Source 2 Source 4
Worker numbers refer to different stages
PowerCo reported around 60 EllisDon workers on site in September and expected around 1,300 at peak. The federal briefing's 3,000 employment figure was reported separately alongside the project announcement. The September count covers one contractor at a point in time and cannot measure eventual operating jobs. Source 3 Source 4
Why the production target matters
The developer says the revised date allows it to align battery technology and the pace of expansion with expected market demand. It continues to build core infrastructure while retaining flexibility about how the plant scales. The 2029 target records that updated development plan. Source 4