Roberts Bank Terminal 2 approval, listing and delivery milestones

Sources checked

The regulatory decision comes before an investment decisionRoberts Bank Terminal 2 approval, listing and delivery milestones
  1. 27 March 2020
    Review panel report submitted

    The panel delivered its report and recommendations Source 7

  2. 20 April 2023
    Federal environmental decision issued

    Original approval required 370 legally binding conditions Source 2

  3. 10 August 2026
    Decision statement administratively updated

    Updated statement posted in the assessment registry Source 1

  4. 29 August 2026
    Potential listing notice published

    Canada Gazette notice preceded the final decision Source 3

  5. 30 October 2026
    National interest listing made

    Order amends Schedule 1 of the Building Canada Act Source 3

  6. Mid-2027 target
    Final investment decision

    Transport Canada describes a viable path to this milestone Source 4

Show 1 more dates
  1. 2035 target
    Commercial operations

    Government's updated forecast, four years ahead of its 2039 comparison Source 4

The October listing is a completed step. The following dates are government targets.

Source 1 Source 2 Source 3 Source 4 Source 5 Source 6 Source 7

Roberts Bank Terminal 2 approval, listing and delivery milestones

The investment decision and commercial operations dates are targets in the October 2026 announcement. The 370 conditions refer to the original 2023 approval.

7 records
Source
27 March 2020Review panel report submittedThe panel delivered its report and recommendationsSource 7
20 April 2023Federal environmental decision issuedOriginal approval required 370 legally binding conditionsSource 2
10 August 2026Decision statement administratively updatedUpdated statement posted in the assessment registrySource 1
29 August 2026Potential listing notice publishedCanada Gazette notice preceded the final decisionSource 3
30 October 2026National interest listing madeOrder amends Schedule 1 of the Building Canada ActSource 3
Mid-2027 targetFinal investment decisionTransport Canada describes a viable path to this milestoneSource 4
2035 targetCommercial operationsGovernment's updated forecast, four years ahead of its 2039 comparisonSource 4