Roberts Bank Terminal 2 was listed in October. The investment decision is next

Canada listed the proposed three-berth Roberts Bank Terminal 2 as a project of national interest on 30 October 2026. Transport Canada is targeting a final investment decision by mid-2027 and commercial operations in 2035.

Sources checked

The regulatory decision comes before an investment decisionRoberts Bank Terminal 2 approval, listing and delivery milestones
  1. 27 March 2020
    Review panel report submitted

    The panel delivered its report and recommendations Source 7

  2. 20 April 2023
    Federal environmental decision issued

    Original approval required 370 legally binding conditions Source 2

  3. 10 August 2026
    Decision statement administratively updated

    Updated statement posted in the assessment registry Source 1

  4. 29 August 2026
    Potential listing notice published

    Canada Gazette notice preceded the final decision Source 3

  5. 30 October 2026
    National interest listing made

    Order amends Schedule 1 of the Building Canada Act Source 3

  6. Mid-2027 target
    Final investment decision

    Transport Canada describes a viable path to this milestone Source 4

Show 1 more dates
  1. 2035 target
    Commercial operations

    Government's updated forecast, four years ahead of its 2039 comparison Source 4

The October listing is a completed step. The following dates are government targets.

Source 1 Source 2 Source 3 Source 4 Source 5 Source 6 Source 7

What the October order actually changes

The order adds the project to Schedule 1 of the Building Canada Act. Its explanatory note says the Act provides the framework for handling remaining applicable federal authorisations. Transport Canada still describes the investment decision as a milestone ahead of the project. Source 3 Source 4

The project's planned capacity is a design measure

Transport Canada describes a three-berth terminal on a new landmass at Roberts Bank in Delta, British Columbia. Its earlier briefing specifies up to 2.4 million additional twenty-foot equivalent units per year at full operation. That is design capacity. The 2035 target describes the intended start of commercial operations. Source 2 Source 5 Source 4

Environmental review remains part of the project record

The original 2023 federal decision imposed 370 legally binding conditions. The October order records the assessment's finding of likely significant adverse effects, including to the endangered Southern Resident Killer Whale population. Transport Canada said the national interest listing maintains existing federal assessment conditions. Source 2 Source 3 Source 4

How Tsawwassen First Nation describes its consent

Tsawwassen First Nation said it consented while continuing to raise concerns about the Fraser estuary and Salish Sea. It identified accommodations for harvesting, environmental protection and ongoing oversight. The order separately records the government's decision that project benefits outweighed potential adverse effects. Source 6 Source 3