How BHP is building Saskatchewan's Jansen potash mine in two stages
BHP reported Jansen's first stage 87% complete on 20 October 2026 and its second stage 18% complete. Its current investment estimates are USD 8.4 billion and USD 6.9 billion respectively.
Sources checked
Investment estimate
Scale · 0 USD billion to 8.4 USD billion
Construction completion
Scale · 0% to 87%
Annual capacity added
Scale · 0 million tonnes to 4.36 million tonnes
Select investment, construction completion or annual capacity. Each measure has its own scale.
The stages add similar capacity on different schedules
BHP expects Stage 1 to start production in mid-2027 and ultimately produce 4.15 million tonnes a year. Stage 2 is expected to begin producing in mid-2031 and add 4.36 million tonnes a year. BHP expects the combined operation to reach full capacity in its 2033 to 2034 financial years. Source 1
The first-stage cost estimate increased from approval
BHP cites a Stage 1 estimate of USD 5.7 billion at sanction and USD 8.4 billion after a detailed review. Its current Stage 2 estimate is USD 6.9 billion. The combined estimate for the two stages is USD 15.3 billion. Source 2 Source 1
Construction progress and operating capacity measure different things
BHP's October construction update puts the first stage at 87% and the second at 18%. These are progress estimates while the mine is under development. Annual capacity applies after commissioning and ramp-up. Source 1
The export chain includes rail and a separate terminal
BHP has agreements with CN and CPKC to carry potash to Westshore Terminals in Delta, British Columbia. An access spur at Jansen connects to both railway networks. The route to the terminal is a separate operational step from extraction and processing at the mine. Source 1